Hello Everyone,
Our construction update for the week of 3/4/2024 is below:
An overall site plan can be found on the last page of the update. This will help readers gain a better understanding of where on-site work is being performed.
During the week of February 26th, the plumbing, electrical, HVAC, and fire protection subcontractors continued installing piping, conduit, hangers, and ductwork in Area’s C and B. Installation of treads, risers, landings and railings continued at Stair #3 and Stair #4. Framing and sheathing of the exterior wall continued at the 4th and 3rd floors in Area’s C & B. Crews continued framing interior walls on the 2nd and 3rd floors in Area C and began in Area B. The concrete subcontractor continued installing mesh & rebar for the slab on decks in Area A and continued preparing the ground floor slab in Area B for concrete. Installation of the roofing system continues in Area B. The mason continued building the CMU block shaft for Elevator #1 in Area B. The site contractor continued excavating for underground conduit & piping in Area A.
Looking ahead to the week of March 4th, the plumbing, electrical, HVAC, and fire protection subcontractors will continue installing piping, conduit, hangers, and ductwork on the upper floors in Area C and Area B. Crews will continue installing tread, risers, and railings for Stair #4 in Area C. At Stair #3, railings and floor infills will be installed. Framing and sheathing of the exterior wall will continue at the 4th and 3rd floors in Area’s C & B, along with framing of the interior walls on the 2nd, 3rd, and 4th floor in Area C and Area B. The concrete subcontractor will continue installing mesh & rebar for the slabs in Area A, along with preparing the slab on grade in Area B for concrete. Roofing installation will continue. Building the masonry elevator shaft will continue. The site contractor will continue excavating and backfilling trenches to support the plumbers and electricians installing their respective piping and conduit.
Trucks, equipment, and deliveries will be a continuous presence at both the north and south gate entrances.
Thank you for your patience and understanding. Please do not hesitate to contact the team with any questions, concerns, or issues. The project team can be reached at: cmsproject@norwoodma.gov