Hello Everyone,
Our construction update for the week of 4/25/2024 is below:
An overall site plan can be found on the last page of the update. This will help readers gain a better understanding of where on-site work is being performed.
During the week of April 22nd, crews continued to frame and sheath the exterior wall at Area’s B & A, along the north & south elevations. Installation of the roofing system continued. Installation of metal windows continued on all floors at the north elevations in Area C. Installation of brick continued at the east and north elevations of Area C. Crews continued framing interior walls on the ground floor in Area C and B along with the 2nd, 3rd, and 4th floors in Area B. Hanging drywall continues on the 2nd floor in Area C. The plumbing, electrical, HVAC, and fire protection subcontractors continued installing piping, conduit, hangers, and ductwork throughout Area’s B and A. 350 cubic yard of concrete was placed this week for the slab on grade in Area A and the stepped seating in the auditorium. The site contractor continues to install the drainage system around the site.
Looking ahead to the week of April 29th, framing and sheathing of the exterior wall will continue at Area B, and Area A. Installation of AVB and metal windows will continue at the north elevation of Area C. The masons will continue to lay brick and masonry block at the exterior of Area C. Roofing installation will continue. On the inside of Area C hanging drywall will continue on the 2nd floor, inwall and above ceiling installation of piping, conduit, and ductwork, along with wall framing and door frame installation will continue on the 3rd and 4th floors. In Area B framing of interior walls and inwall and above ceiling installation of piping, conduit, and ductwork continues on all floors. In Area C installation of above ceiling of piping, conduit, and ductwork will continue as framing for interior walls begins.
Trucks, equipment, and deliveries will be a continuous presence at both the north and south gate entrances.
Thank you for your patience and understanding. Please do not hesitate to contact the team with any questions, concerns, or issues. The project team can be reached at: cmsproject@norwoodma.gov