Construction Update 03-29-2024

Construction Update 03-29-2024

Hello Everyone,

Our construction update for the week of 3/29/2024 is below:

An overall site plan can be found on the last page of the update. This will help readers gain a better understanding of where on-site work is being performed.

During the week of March 25th, crews continue to focus on enclosing the building, installation of the roof system continued in Area B. Framing and sheathing of the exterior wall continued at Area’s C & B during the first half of the week, but rain Thursday & Friday forced these crews to focus on interior framing. Installation of metal windows continued at the east elevation in Area C. Crews continued framing interior walls on all floors in Areas C and on the 2nd, 3rd, and 4th floors in Area B. The plumbing, electrical, HVAC, and fire protection subcontractors continued installing piping, conduit, hangers, and ductwork in Area’s C and B, while installing underground drainage piping and electrical conduit in Area A. The concrete subcontractor poured concrete at Stair #1 in Area A, Stair #2 in Area B, and Roof pads at Area A, while also continuing to prepare the Auditorium and 2nd floor slab on deck in Area A for concrete. The site contractor continued excavating/backfilling in Area A for underground conduit & piping along with installation of site drainage structures and associated piping.

 

Looking ahead to the week of April 1st, crews from the mechanical trades will continue installing piping, conduit, hangers, and ductwork in Area C and Area B. Framing and sheathing of the exterior wall will continue at Area C and B, and begin in Area A. Installation of AVB and metal windows will continue in Area C. Framing of the interior walls on the ground, 2nd, 3rd, and 4th floors in Area C and Area B, hanging drywall at the tops of walls continues on the upper floors in Area C. The concrete subcontractor will continue preparing areas for concrete, with plans to pour the slab on deck on the 2nd floor in Area A, the finally the Auditorium Stadium Seating/Orchestra Pit. Roofing installation will continue. The site contractor will continue excavating and backfilling trenches to support the plumbers and electricians installing their respective piping and conduit while also continuing to install drainage structures and associated piping.

Trucks, equipment, and deliveries will be a continuous presence at both the north and south gate entrances.

Thank you for your patience and understanding. Please do not hesitate to contact the team with any questions, concerns, or issues. The project team can be reached at: cmsproject@norwoodma.gov