Construction Update 9-8-23

Hello Everyone,
Our construction update for the week of 9/8/2023 is below:

An overall site plan can be found on the last page of the update. This will help readers gain a better understanding of where on-site work is being performed. During the week of September 4th, WTR and their subcontractors continue to prepare for and install foundations in Area B and Area A. Installation of rebar and formwork for foundation footings & walls in Area B continue and have begun in Area A.. The site contractor continues to excavate from grade to bottom of footing elevation in Area A, ahead of the concrete subcontractor. Following the concrete pours, formwork from the pours are removed, drainage pipe is installed at the base of the walls, and the walls backfilled.

Looking ahead to the week of September 11th, the site contractor will continue excavating to bottom of footing elevation in Area B and Area A ahead of the concrete subcontractor installing rebar and formwork for foundation footings and walls. The site contractor will excavate for installation of the grease trap and for electrical conduit to the main electrical room.

Trucks, equipment, and deliveries will be a continuous presence at both the north and south gate entrances.

Thank you for your patience and understanding. Please do not hesitate to contact the team with any questions, concerns, or issues. The project team can be reached at: cmsproject@norwoodma.gov

impacts and logistics 9-8-23